Unitary Status Settlement Update April 12, 2017 Facilities Services
Unitary Status Settlement Agreement This Agreement provides the framework for accomplishing that goal in a manner that is consistent with applicable legal principles and decisions of the Supreme Court and is fair, reasonable, adequate and equitable to all parties 2
Paragraph 2 of the Settlement Agreement titled, Replacement Projects Scheduled for Fiscal Year 2010, states that: The following school replacement projects, scheduled for Fiscal Year 2010 in the Tentative Capital Outlay Budget approved by the Orange County School Board on September 8, 2009, shall be completed on a timely basis and in accordance with the building standards articulated in paragraph 1 herein: (2) Projects with funding available in 2010 (at the time of the agreement) Status Sales Tax Priority Agreement Requirement Actual Completion Year College Park Middle School* Complete 22 timely manner 2010 Orange Center Elementary School Complete 47 timely manner 2011 Evans High School Complete 83 timely manner 2011 Oak Ridge High School Complete 67 timely manner 2013 * Renamed- formerly Lee Middle School 3
Paragraph 4 of the Settlement Agreement titled, School Renovations/Addition/ Replacement Projects Scheduled for Fiscal Years 2012-2016, states that: The amended or supplemented replacement/renovation/addition projects developed through the process described above, in each instance, be completed as close to the originally scheduled date as possible, or earlier if possible. (4) Projects with funding available in 2012-2016 (at the time of the agreement) Status Sales Tax Priority Agreement Requirement Projected / Actual Completion Year Eccleston Elementary School Complete 67 2012-2016 2013 Pineloch Elementary School Complete 79 2012-2016 2014 Wheatley Elementary School Complete 86 2012-2016 2014 Grand Ave/OCPS Academic Center for Excellence (ACE) Construction 74 2012-2016 * 2017 Carver Middle School Construction 90 2012-2016 * 2017 Tangelo Park Elementary School Complete 91 2012-2016 2016 * Actual construction start date is within the range (FY 2012 - FY 2016) stipulated in Paragraph four (4) of the original agreement although the projected completion year (2017) does not 4
Paragraph 5 of the Settlement Agreement titled, Additional Replacement/Renovation/ Addition Projects, states that: The replacement/renovation/addition projects developed through the process described in this paragraph shall be scheduled for commencement and completion as early as possible consistent with the other capital construction needs of the school system. (5) Projects with funding available after 2016 (at the time of the agreement) Status Sales Tax Priority Agreement Requirement Projected Completion Washington Shores Elementary School Complete 97 as early as possible 2014 Washington Shores Primary Learning Center * Design 110 as early as possible 2017 Rock Lake Elementary School Construction 102 as early as possible 2017 Mollie Ray Elementary School Construction 114 as early as possible 2017 Ivey Lane Elementary School Construction 117 as early as possible 2017 Maxey Elementary School Design 127 as early as possible 2018 Hungerford Elementary School Design 129 as early as possible 2018 * Repurposed - formerly Richmond Heights Elementary 5
Unitary Status Schools No. Name Planned Year Opening 74 OCPS Academic Center for Excellence 2017 90 Carver MS 2017 102 Rock Lake ES 2017 94 Engelwood ES 2017 110 Washington Shores PLC ** 2017 96 Oak Hill ES 2017 114 Mollie Ray ES 2017 122 Meadow Woods ES *** 2017 117 Ivey Lane ES 2017 123 Ventura ES *** 2017 92 Dover Shores ES 2018 127 Maxey ES 2018 93 Cypress Park ES 2018 129 Hungerford ES 2018 95 Audubon Park ES * 2018 98 Lake Como/ Kaley K8 2018 99 Hillcrest ES 2018 105 Union Park ES 2018 106 Pine Hills ES 2018 124 Frangus ES *** 2018 130 Hidden Oaks ES *** 2018 Unitary Status School * Priority 95 to be funded as Relief School 133-K8-E-6 ** Priority 110 repurposed to Washington Shores PLC (Formerly Richmond Heights ES) *** Accelerated Project 6