CHAPTER 4 MODELING SIMULATION AND ANALYSIS OF PROJECTS USING MICROSOFT EXCEL AND SIMQUICK
|
|
- Lizbeth Boone
- 6 years ago
- Views:
Transcription
1 63 CHAPTER 4 MODELING SIMULATION AND ANALYSIS OF PROJECTS USING MICROSOFT EXCEL AND SIMQUICK 4.1 INTRODUCTION Section describes modeling and Simulation, analysis of projects using Microsoft Excel, the characteristics of the proposed Excel model for representing projects presented in section The various stages of simulation software such as project planning, project analysis are discussed. Also validation of Excel simulation software with product development project example presented in Section 4.2 and describes the application of SimQuick for modeling and simulation of project. Summary is presented in section Simulation using Microsoft Excel In this section an extended PERT simulation of the product development process is proposed. The simulation model is constructed in Microsoft Excel. The expected project completion time and percentage utilization of resources are evaluated. The assumptions of the model are Activities are performed in a particular topological order. A list of activities in a project is said to be in topological order if no activities appear in the list before all of its immediate predecessors have appeared. For the activities in Figure 4.1 the possible topological orders are a-b-c-d-e, a-b-d-c-e and a-c-b-d-e.
2 64 Figure 4.1 Sample network Task duration is random and follows triangular distribution and is shown in Figure 4.2 Three time estimates are required to compute parameters of activity duration. Optimistic time (To): It is the duration of any activity when everything goes on very well during the project. Most likely time (Tm): It is the duration of any activity when sometimes things go on very well, sometimes things go on very bad while doing the project. Pessimistic time (Tp): It is the duration of any activity when almost everything goes against our will and a lot of difficulties are faced while doing a project. Figure 4.2 Triangular distribution where, x is a Random variable; f (x) is the probability density function; 2( x To) f ( x) =, To x Tm ; ( Tp To)( Tm To) 2(Tm Tx) f (x) =, (Tp To)(Tp Tm) Tm x Tp ; f (x) = 0, Else
3 65 The availability of resources is random and assumed to follow uniform distribution and is shown in Figure 4.3. Figure 4.3 Uniform distribution The activities are scheduled as per the topological order. If an activity needs a revision due to iteration, then rescheduling of activities and resources will be done as per topological order. If more than one activity becomes eligible and they are not sharing common resources they can start simultaneously. Otherwise forthcoming activity should wait to allocated resource to become free. Interruptions can occur at any stage of PD process. It may occur due to break down of machineries, unavailability of resources, etc. The flow chart of extended PERT simulation for PD process is shown in Figure 4.4
4 66 Figure 4.4 Flowchart showing the simulation details in excel simulation
5 Steps in simulation The proposed model employs a discrete event simulation to estimate the completion time of projects. Analytical features are included so that the model can describe the complex behavior of development process. Step 1 : Enter the following Number of activities N Topological order Number of resources m required for each activity Optimistic (To), most likely (Tm) and pessimistic timings (Tp) Rework probabilities Probability range of impact for each activity Step 2 : Activity =1, find resources involved in activity 1. Early start=0 Resource ready time=0 Delay=0 Processing time=triangular (To, Tm, Tp) Early finish= Processing time Step 3 : New activity= Next activity in topological order Step 4 : Find resources involved in New Activity Early start=maximum (Resources ready time) If Delay occur Then Delay=Uniform (a, b) Else Delay=0 Processing time=triangular (To, Tm,Tp) Early finish= Early start + Processing time + Delay Step 5 : Find rework count to corresponding activity If rework exist then Step 6 Else Step 7 Step 6 : Find impact probability Rework count=rework count +1 for corresponding activity Find impact activity New activity= Impact activity
6 68 Go to step 4 Step 7 : If (Activity=Final activity N) Then Step 8 Else Step 3 Step 8 : Print Completion time=, Earliest finish time Step 9 : Print Each Resource usage time Step10 : STOP where Triangular (To, Tm, Tp) is a user defined function which gives value as per definition given in task duration. Uniform (a, b) is a user defined function which gives value as per definition given in delays due to interruptions Case Study A case study from an engineering industry is detailed below. This industry has a research and development (R&D) wing to deal with PD on a continuous basis. The project consists of 11 activities and the immediate predecessor relationships and duration of activities are shown in Table The model has assumed that activity duration follows triangular distribution. Table 4.1 Details of case study for excel simulation Activity To Tm Tp Resources Activity Predecessor No. (Weeks) r1 r2 r3 1 Concept Development Design Specifications Materials Methods Tooling Test Development Train 4, Prototype 4, Testing 7, Launch 9,
7 69 The network diagram is given in Figure 4.4. Figure 4.5 Project network used for excel simulation The model is simulated with uncertainty of durations, resource allocations and scheduling. The snap shot of the model in Microsoft Excel is shown in Figure 4.5.The topological order taken is It is simulated for 1000 runs Summary Modeling and simulating product development process by considering uncertainty of activity durations, iterations with learning, interruption and resource scheduling conflicts will make estimate close to reality. The statistical measure observed from simulation without considering iteration is as shown in Table 4.2. The distribution of completion time over the simulation and its corresponding probability of success are as shown in Figure 4.6 The utilization of resource over the simulation is shown in Figure 4.7.a, 4.8.b and 4.9.c. The probable completion time is in the range of weeks and corresponding probability of success is in the range of 0.55 to The associated risk is 25-45%. Since iteration is not considered this estimate is not realistic.
8 70 Figure 4.6 Snap shot of the model in microsoft excel Table 4.2 Details of statistical measures for excel simulation Median 38 Mode 35 Standard Deviation Sample Variance Kurtosis Skewness Range 74 Minimum 28 Maximum 102 Sum Count Largest(1) 102 Smallest(1) 28 Confidence Level (95.0%)
9 71 Figure 4.7 Histogram of completion time and cumulative probability of success for projects modeled in microsoft excel Figure 4.8 (a) Utilization of resource R1
10 72 Figure 4.8 (b) Utilization of resource R2 Figure 4.8(c) Utilization of resource R3 With the following additional data new model has constructed. Interruptions are assumed to distribute between 0.2 to0.8 weeks. Rework probabilities with learning for each task are as shown in Table 4.3.
11 73 Activity no Table 4.3 Rework probability with learning Rework 1 Rework 2 Rework 3 and above The statistical measure for 1000 simulation is shown in Table 4.4. The distribution of completion time and corresponding probability of success are as shown in Figure 4.8. The utilization of resourcess is shown in Figure 4.9.a, 4.9.b and 4.9.c respectively. Figure 4.9 Histogram of completion time and cumulative probability of success (with rework)
12 74 Table 4.4 Statistical measures with rework Mean Standard Error Median Mode 92 Standardd Deviation Sample Variance Kurtosis Skewness Range Minimum Maximum Sum Count Largest(1) Smallest(1) Confidence Level(95.0%) Figure 4.10 (a) Utilization of resource R1 with rework
13 75 Figure 4.10 (b) Utilization of resource R2 with rework Figure 4.10 (c) Utilization of resource R3 with rework The histogram of completion time in Figure4.9 shows that the completion time is in the range of weeks. Its probability of success is The associated risk is 45-50%. When rework is taken into consideration, it is observed that the PD completion time has increased and the probability of successs has reduced. Since the constructed model is close to reality, this estimate is more realistic and reliable. In order to resource 3 capacities avoid waiting of activities for resources, resource 2 and have increased to two. Then the model is simulated for
14 times. The resultant statistical measures are shown in Table 4.5 and distribution of completion time is shown in Figure The completion time will be in the range of weeks. Its corresponding probability of success is To complete within 140 weeks, probability of success is Resultant utilization of resources are as shown in Figure 4.11.a, 4.11.b, 4.11.c. Significance of improvement by this proposed method is validated using Test of significance for difference of means of two large samples. X 1 = Mean (Statistical measures, Table 4.5) X 2 = Mean (Statistical measures, Table 4.6) n1 n2 = Sample size (No. of simulation runs =Count, Statistical measures Table 4.5) = Sample size (No. of simulation runs =Count, Statistical measures Table4. 6) s 1 = Standard deviation (Statistical measures Table4. 2) s 2 = Standard deviation (Statistical measures Table4. 2) Null hypothesis Ho: Two samples have been drawn from the same population ( X 1 = X 2 ) Table 4.5 Statistical measures with increased capacity of resources Mean Standard Error Median Mode Standard Deviation Sample Variance Kurtosis Skewness Range Minimum Maximum Sum Count 1000 Largest(1) Smallest(1) Confidence Level(95.0%)
15 77 Alternate hypothesis H1: ( X 1 X 2 ) The Test statistics is z = X 1 X s1 s2 + n1 n2 The value of z is calculated as The critical value of z corresponding to 5% level of significance is 1.64 for one tailed test and 1.96 for two tailed test. The corresponding value for 1% level of significance is 2.33 and Since the value of z is greater than the standardd value (critical value) for both the cases, the difference is highly significant. Hence, the null hypothesis is rejected. Therefore we can conclude that significant difference is attained by increasing the resource capacity. Figure 4.11 Histogram of completion time and cumulative probability of success (with increased capacity of resources)
16 78 Figure 4.12(a) Utilization of resource R1 with increased resource capacity Figure 4.12(b) Utilization of resource R2 with increased resource capacity
17 79 Figure 4.12(c) Utilization of resource R3 with increased resource capacity 4.2 SIMULATION USING SIMQUICK This section describes the application of SimQuick for modeling and simulation of project. The completion time of the project is estimated for unconstrained and constrained resource environments. Assumptions of the model are Activities are performed in a particular topological order Task duration of each activity is random The basic steps involved in this methodology are 1. Conceptually build a model of the process using the building blocks of SimQuick. 2. Enter this conceptual model into SimQuick 3. Test process improvement ideas with the model Building blocks and control panel in SimQuick: The five building blocks used in SimQuick simulation are Entrance, Exit, Workstation, Buffers and Decision points. The output results can obtain in View Results. The control panel of the SimQuick window is shown in Figure Each
18 80 button transfers control to a work sheet containing the SimQuick tables through which one specifies a simulation. Figure 4.13 Simquick control panel Entrance: Arrival of entity is defined by Entrance block. This is where objects enter the process. Inputs to this block are Time between arrivals and Objects per arrival. Time between arrivals is defined by appropriate probability distribution. Objects per arrival define number of entities entering the system. Objects leaving this block are guided by the Output destination Workstation: Processing of entity is defined by workstation. Input to this block is the Working time of the workstation, which is defined by the appropriate distribution. Objects leaving this block are guided by the Output destination. Resourcee involved in that process can also defined by Resource Name and Resourcess needed.
19 81 Buffers: This is where objects can be stored. Buffer can represent a location in a where house or factory where inventory can be stored, or a place where people can stand on line at a post office, etc. It is used as storage counting block. Input to this block is how many objects it can hold. It counts number of objects entering buffer. Thus it is defined to determine average entities leaving system. For our project purpose Capacity value assigned is one. Simulation control: It is used to define time units per simulation and number of simulations Case Study A typical case study from an engineering industry is presented. The list of various activities, immediate predecessor relationship, activity durations and the resource required (man power) to complete the activity are detailed in Table 4.6. The activities in the project are considered as the jobs and resources are considered as workstations in the process. The details of the model parameters are shown in Table 4.7.
20 82 Activity A Description of activity Concept development Table 4.6 Project details under study Immediate predecessors Expected duration Resource (days) required T o T m T p _ B Concept testing A C System level design B D Detailed design C E Implement modifications C F Product drawing E G Conceptual mapping. C H Stage drawing F I Trial planning D J Get customer feed back H,I K Tool plan manufacturing C L Pre- launch plan K M Training L N Build prototype M,J O Product trail N P Capability studies O Q Debug faults P R Certify the product Q S Initial production run P T Prepare for advertisement S U Roll out final product-launch T,R,G
21 83 Table 4.7 Details of model parameters for the project under study for simulation using simquick Control name Activity name Input parameters Output destinations Resource Units needed Workstation A Working time = Nor(12,2) B, Output Objects =1 6 Workstation B Working time = Nor(15.33) C, Output Objects =1 8 D, Output Objects =1 Workstation Working time = Nor(3,1) E, Output Objects =1 G, Output Objects =1 2 K, Output Objects =1 Workstation D Working time = Nor(6,2) I, Output Objects =1 3 Workstation E Working time = Nor(12,2) F, Output Objects =1 6 Workstation G Working time = Nor(15.67,5.13) U, Output Objects =1 9 Workstation F Working time = Nor(24,3.6) H, Output Objects =1 10 Workstation H Working time = Uni (5,7) J, Output Objects =1 3 Workstation I Working time = Nor(11,3.6) J, Output Objects =1 6 Workstation J Working time = Nor(17,3) N, Output Objects =1 9 Workstation K Working time = Nor(2,1) L, Output Objects =1 1 Workstation L Working time = Nor(15,5) M, Output Objects= 1 8 Workstation M Working time = Nor(5,2) N, Output Objects =1 3 Workstation N Working time = Nor(15,2) O, Output Objects =1 8 Workstation O Working time = Nor(3,1) P, Output Objects =1 2 Workstation P Working time = Nor(10,3.61) Q, Output Objects =1 S, Output Objects =1 5 Workstation Q Working time = Constant(2) R, Output Objects =1 2 Workstation R Working time = Nor(2,2) U, Output Objects =1 1 Workstation S Working time = Nor(10,3) T, Output Objects =1 5 Workstation T Working time = Nor(7,2) U, Output Objects =1 4 Workstation U Working time = Nor(8,4) End, Output objects=1 4 Buffer Start Capacity =1;Initial objects=1 A, Output Objects =1 - Buffer End Capacity =1;Initial objects=0 - -
22 84 With these model parameters, the process is simulated for 200 runs. A typical spreadsheet simulation input is shown in Figure The process simulation is done for unlimited resource environment and constrained resource environment Model View (Note: Cannot edit model here) Simulation controls: Time units per simulation 500 Number of simulations 200 Work Stations: 1 Name a Working time Nor(12,2) Output # of output Resource Resource destination(s) objects name(s) # units needed B 1 za 6 2 Name b Working time Nor(15.33,1.53) Output # of output Resource Resource destination(s) objects name(s) # units needed C 1 za 8 Figure 4.14 Typical spread sheet simulation input for project In the constrained resource environment, the man power availability is considered and is assumed that maximum available man power is 15. The completion time of the project is calculated for both cases and histograms of completion time are plotted. By setting the model parameters, the process is
23 85 simulated for 200 runs. Time units per simulation are taken as 500.Mean inventory at the end is the fraction of time during the simulation that the project is completed. Project duration (PD completion time) = (1-mean inventory at the end)*(simulation duration) In the case of unlimited resource environment, mean inventory at the end = ; project completion time= ( )*500= days. In the case of limited resources, Mean inventory at the end = project completion time = ( )*500=183.2 days. By this method completion time of the project is calculated and is tabulated in Table 4.8 and 4.9 respectively. Table 4.8 Project completion time under unlimited resources
24 86 Table 4.9 Project completion time under constrained resources Summary The project is modeled and simulated using SimQuick. The completion time of the Project is computed in the unlimited and constrained resource environments separately. The histogram of completion time is plotted in Figure 4.14 and 4.15 respectively.
25 87 Based on simulation the histogram of project completion time under unlimited resource environment is shown in Figure The project gets good chance of completion within 166 days. But in reality the resources are limited. For simulating the real time behavior, the available man power is limited to 15 and the simulation results are presented in Figure The completion time of the project in this case is 188 days. Figure 4.15 Frequency histogram of project completion time with unlimited resources Figure 4.16 Frequency histogram of project completion time under constrained resources
26 COST MANAGEMENT IN PROJECTS USING SIMULATION To reduce a project completion time, additional resources for activities along the critical path of the project network is used and the technique is called crashing. The computer simulation model is developed using spread sheet to determine the order in which activities should be crashed as well as the optimal crashing strategy for a project network. The objective is to obtain the optimal crashing configuration to minimize the total project cost.the procedure is as follows. Prepare a simulation model of the project network Identify the potential/ feasibility of crashing each activity in the network and the related costs. Utilize a spread sheet simulation optimization tool to determine the optimal project crashing configuration. The simulation model is used to determine the project duration and the additional project cost (crash + penalty costs). The crashing procedure is illustrated by using the case example reported in the literature (Haga 1998). The project network is shown in Figure 4.16 The activity details of the network along with the precedence relationships are listed in Table 4.9 The activities on this critical path each have a potential of crashing up to 3 time units. The respective parameters of the activity time distributions and unit crashing costs are listed in Table The target completion time of the project is 180. The equation defining the penalty cost for late completion is 0, if T 180 p = 10( T 180), if T 180 where T is the resulting completion time of the project The projects without crashing and optimal crashing configuration were simulated 1000 times to generate the distribution of completion time as
27 89 in Figure and the cumulative distribution of the total project cost as in Figure 4.18 Table 4.11 tabulated the average, standard deviation of the project duration and project cost. Figure 4.17 Manufacturing project network example under study for crashing Table 4.10 Input details for manufacturing project network under study Activity Predecessor Activity Predecessors , , , , , , , , , ,22, , , , ,31, , , , ,35
28 90 16% 14% Probability 12% 10% 8% 6% Original Optimal 4% 2% 0% Duration Figure 4.18 Probability of project completion time Table 4.11 Time estimates and crashing cost for the project activities Activity To Tm Tp Crash cost T 0 -Optimistic time T m- Most likely time T p- Pessimistic time
29 91 Cum m ulative% 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% Original Optimal Cost Figure 4.19 Cumulative distribution of the project cost Table 4.12 Comparison between project duration and cost without crashing and with crashing Project duration Project Cost Average Std.Dev. Average Std. Dev. Original Optimal Cost management of projects by Net Present Value (NPV): The expected return on capital for project is the cost of capital. The values of the future net incomes discounted by the cost of the capital are project net present value. The financial success of projects can be efficiently analyzed with simulation. The use of spread sheet simulation for estimating net present value of the project is illustrated. Case example: A car manufacturing company is developing a new model of compact car; this car is assumed to generate sales for the next five years. It has gathered information about the following quantities through focus
30 92 groups with the marketing and engineering departments. Fixed cost of the car is assumed to be rupees 1.4 crore.the fixed cost is incurred at the beginning of year 1, before any sales are recorded. Margin per car is the unit selling price minus the variable cost of producing car. The manufacturer assumes that in year 1, the margin will decrease by 4%.The demand for the sales of the car are the uncertain quantity. The car manufacturer assumes sales-number of car sold in the first year is triangularly distributed with parameters for rupees100000, , and Every year after that, the company assumes sales will decrease by some percentage where this percentage is triangularly distributed with parameters 5%, 8% and 10%.The company also assumes the percentage decreases in successive years are independent of one another. Depreciation and taxes of the company depreciates its development cost on a straight line basis over the lifetime of the car. The corporate tax rate is 40%. Discount rate Figs are cost of capital at 15%. The spread sheet model is developed as shown in Figure 3.11 and by simulation NPV of the project is estimated. 4.4 SUMMARY This chapter presents modeling and simulation of projects using Excel has presented a generic model to estimate completion time and associated probability of success by capturing characteristics of projects such as iterations, uncertainties of durations, delays, complex resource allocation and scheduling. The simulation is performed with and without considering rework probability. Expected Project completion time and resource utilization are evaluated. Using SimQuick simulation software, the Product development project is simulated with unlimited resource environment and constrained resource environment. Simulation can successfully utilized for finding net present value of the projects.
Task Types. Duration, Work and Units Prepared by
Task Types Duration, Work and Units Prepared by 1 Introduction Microsoft Project allows tasks with fixed work, fixed duration, or fixed units. Many people ask questions about changes in these values when
More informationAn Introduction to Simio for Beginners
An Introduction to Simio for Beginners C. Dennis Pegden, Ph.D. This white paper is intended to introduce Simio to a user new to simulation. It is intended for the manufacturing engineer, hospital quality
More informationProbability and Statistics Curriculum Pacing Guide
Unit 1 Terms PS.SPMJ.3 PS.SPMJ.5 Plan and conduct a survey to answer a statistical question. Recognize how the plan addresses sampling technique, randomization, measurement of experimental error and methods
More informationMajor Milestones, Team Activities, and Individual Deliverables
Major Milestones, Team Activities, and Individual Deliverables Milestone #1: Team Semester Proposal Your team should write a proposal that describes project objectives, existing relevant technology, engineering
More informationSTA 225: Introductory Statistics (CT)
Marshall University College of Science Mathematics Department STA 225: Introductory Statistics (CT) Course catalog description A critical thinking course in applied statistical reasoning covering basic
More informationVisit us at:
White Paper Integrating Six Sigma and Software Testing Process for Removal of Wastage & Optimizing Resource Utilization 24 October 2013 With resources working for extended hours and in a pressurized environment,
More informationSoftware Maintenance
1 What is Software Maintenance? Software Maintenance is a very broad activity that includes error corrections, enhancements of capabilities, deletion of obsolete capabilities, and optimization. 2 Categories
More informationMeasurement & Analysis in the Real World
Measurement & Analysis in the Real World Tools for Cleaning Messy Data Will Hayes SEI Robert Stoddard SEI Rhonda Brown SEI Software Solutions Conference 2015 November 16 18, 2015 Copyright 2015 Carnegie
More informationThe Good Judgment Project: A large scale test of different methods of combining expert predictions
The Good Judgment Project: A large scale test of different methods of combining expert predictions Lyle Ungar, Barb Mellors, Jon Baron, Phil Tetlock, Jaime Ramos, Sam Swift The University of Pennsylvania
More informationM55205-Mastering Microsoft Project 2016
M55205-Mastering Microsoft Project 2016 Course Number: M55205 Category: Desktop Applications Duration: 3 days Certification: Exam 70-343 Overview This three-day, instructor-led course is intended for individuals
More informationIntroduction to Simulation
Introduction to Simulation Spring 2010 Dr. Louis Luangkesorn University of Pittsburgh January 19, 2010 Dr. Louis Luangkesorn ( University of Pittsburgh ) Introduction to Simulation January 19, 2010 1 /
More informationCertified Six Sigma Professionals International Certification Courses in Six Sigma Green Belt
Certification Singapore Institute Certified Six Sigma Professionals Certification Courses in Six Sigma Green Belt ly Licensed Course for Process Improvement/ Assurance Managers and Engineers Leading the
More informationAlgebra 1, Quarter 3, Unit 3.1. Line of Best Fit. Overview
Algebra 1, Quarter 3, Unit 3.1 Line of Best Fit Overview Number of instructional days 6 (1 day assessment) (1 day = 45 minutes) Content to be learned Analyze scatter plots and construct the line of best
More informationPM tutor. Estimate Activity Durations Part 2. Presented by Dipo Tepede, PMP, SSBB, MBA. Empowering Excellence. Powered by POeT Solvers Limited
PM tutor Empowering Excellence Estimate Activity Durations Part 2 Presented by Dipo Tepede, PMP, SSBB, MBA This presentation is copyright 2009 by POeT Solvers Limited. All rights reserved. This presentation
More informationEdexcel GCSE. Statistics 1389 Paper 1H. June Mark Scheme. Statistics Edexcel GCSE
Edexcel GCSE Statistics 1389 Paper 1H June 2007 Mark Scheme Edexcel GCSE Statistics 1389 NOTES ON MARKING PRINCIPLES 1 Types of mark M marks: method marks A marks: accuracy marks B marks: unconditional
More informationOn the Combined Behavior of Autonomous Resource Management Agents
On the Combined Behavior of Autonomous Resource Management Agents Siri Fagernes 1 and Alva L. Couch 2 1 Faculty of Engineering Oslo University College Oslo, Norway siri.fagernes@iu.hio.no 2 Computer Science
More informationDecision Analysis. Decision-Making Problem. Decision Analysis. Part 1 Decision Analysis and Decision Tables. Decision Analysis, Part 1
Decision Support: Decision Analysis Jožef Stefan International Postgraduate School, Ljubljana Programme: Information and Communication Technologies [ICT3] Course Web Page: http://kt.ijs.si/markobohanec/ds/ds.html
More informationUniversity of Groningen. Systemen, planning, netwerken Bosman, Aart
University of Groningen Systemen, planning, netwerken Bosman, Aart IMPORTANT NOTE: You are advised to consult the publisher's version (publisher's PDF) if you wish to cite from it. Please check the document
More informationReduce the Failure Rate of the Screwing Process with Six Sigma Approach
Proceedings of the 2014 International Conference on Industrial Engineering and Operations Management Bali, Indonesia, January 7 9, 2014 Reduce the Failure Rate of the Screwing Process with Six Sigma Approach
More informationExecutive Guide to Simulation for Health
Executive Guide to Simulation for Health Simulation is used by Healthcare and Human Service organizations across the World to improve their systems of care and reduce costs. Simulation offers evidence
More informationSchool of Innovative Technologies and Engineering
School of Innovative Technologies and Engineering Department of Applied Mathematical Sciences Proficiency Course in MATLAB COURSE DOCUMENT VERSION 1.0 PCMv1.0 July 2012 University of Technology, Mauritius
More informationTitle:A Flexible Simulation Platform to Quantify and Manage Emergency Department Crowding
Author's response to reviews Title:A Flexible Simulation Platform to Quantify and Manage Emergency Department Crowding Authors: Joshua E Hurwitz (jehurwitz@ufl.edu) Jo Ann Lee (joann5@ufl.edu) Kenneth
More informationGrade 6: Correlated to AGS Basic Math Skills
Grade 6: Correlated to AGS Basic Math Skills Grade 6: Standard 1 Number Sense Students compare and order positive and negative integers, decimals, fractions, and mixed numbers. They find multiples and
More informationMKTG 611- Marketing Management The Wharton School, University of Pennsylvania Fall 2016
MKTG 611- Marketing Management The Wharton School, University of Pennsylvania Fall 2016 Professor Jonah Berger and Professor Barbara Kahn Teaching Assistants: Nashvia Alvi nashvia@wharton.upenn.edu Puranmalka
More informationSTABILISATION AND PROCESS IMPROVEMENT IN NAB
STABILISATION AND PROCESS IMPROVEMENT IN NAB Authors: Nicole Warren Quality & Process Change Manager, Bachelor of Engineering (Hons) and Science Peter Atanasovski - Quality & Process Change Manager, Bachelor
More informationDiagnostic Test. Middle School Mathematics
Diagnostic Test Middle School Mathematics Copyright 2010 XAMonline, Inc. All rights reserved. No part of the material protected by this copyright notice may be reproduced or utilized in any form or by
More informationCHAPTER 4: REIMBURSEMENT STRATEGIES 24
CHAPTER 4: REIMBURSEMENT STRATEGIES 24 INTRODUCTION Once state level policymakers have decided to implement and pay for CSR, one issue they face is simply how to calculate the reimbursements to districts
More informationWIC Contract Spillover Effects
WIC Contract Spillover Effects Rui Huang* Jeffrey M. Perloff** June 2012 * Corresponding author: Assistant Professor, Department of Agricultural and Resource Economics, University of Connecticut. Mailing
More informationSAP EDUCATION SAMPLE QUESTIONS: C_TPLM40_65. Questions. In the audit structure, what can link an audit and a quality notification?
SAP EDUCATION SAMPLE QUESTIONS: C_TPLM40_65 SAP Certified Application Associate Quality Management with SAP ERP 6.0 EhP5 Disclaimer: These sample questions are for self-evaluation purposes only and do
More informationA GENERIC SPLIT PROCESS MODEL FOR ASSET MANAGEMENT DECISION-MAKING
A GENERIC SPLIT PROCESS MODEL FOR ASSET MANAGEMENT DECISION-MAKING Yong Sun, a * Colin Fidge b and Lin Ma a a CRC for Integrated Engineering Asset Management, School of Engineering Systems, Queensland
More informationAlgebra 2- Semester 2 Review
Name Block Date Algebra 2- Semester 2 Review Non-Calculator 5.4 1. Consider the function f x 1 x 2. a) Describe the transformation of the graph of y 1 x. b) Identify the asymptotes. c) What is the domain
More informationValue Creation Through! Integration Workshop! Value Stream Analysis and Mapping for PD! January 31, 2002!
Presented by:! Hugh McManus for Rich Millard! MIT! Value Creation Through! Integration Workshop! Value Stream Analysis and Mapping for PD!!!! January 31, 2002! Steps in Lean Thinking (Womack and Jones)!
More informationUNIT ONE Tools of Algebra
UNIT ONE Tools of Algebra Subject: Algebra 1 Grade: 9 th 10 th Standards and Benchmarks: 1 a, b,e; 3 a, b; 4 a, b; Overview My Lessons are following the first unit from Prentice Hall Algebra 1 1. Students
More informationGreen Belt Curriculum (This workshop can also be conducted on-site, subject to price change and number of participants)
Green Belt Curriculum (This workshop can also be conducted on-site, subject to price change and number of participants) Notes: 1. We use Mini-Tab in this workshop. Mini-tab is available for free trail
More informationMGT/MGP/MGB 261: Investment Analysis
UNIVERSITY OF CALIFORNIA, DAVIS GRADUATE SCHOOL OF MANAGEMENT SYLLABUS for Fall 2014 MGT/MGP/MGB 261: Investment Analysis Daytime MBA: Tu 12:00p.m. - 3:00 p.m. Location: 1302 Gallagher (CRN: 51489) Sacramento
More informationFundamental Accounting Principles, 21st Edition Author(s): Wild, John; Shaw, Ken; Chiappetta, Barbara ISBN-13:
Dakota College at Course Syllabus Course Prefix/Number/Title: ACCT 200 Elements of Accounting I Credits: 3 Instructor: Kara Bowen Office: Thatcher Hall 109, Bottineau campus Phone: 701 228 5432 Email:
More informationLecture 1: Machine Learning Basics
1/69 Lecture 1: Machine Learning Basics Ali Harakeh University of Waterloo WAVE Lab ali.harakeh@uwaterloo.ca May 1, 2017 2/69 Overview 1 Learning Algorithms 2 Capacity, Overfitting, and Underfitting 3
More informationMath 121 Fundamentals of Mathematics I
I. Course Description: Math 121 Fundamentals of Mathematics I Math 121 is a general course in the fundamentals of mathematics. It includes a study of concepts of numbers and fundamental operations with
More informationSTT 231 Test 1. Fill in the Letter of Your Choice to Each Question in the Scantron. Each question is worth 2 point.
STT 231 Test 1 Fill in the Letter of Your Choice to Each Question in the Scantron. Each question is worth 2 point. 1. A professor has kept records on grades that students have earned in his class. If he
More informationCONSTRUCTION OF AN ACHIEVEMENT TEST Introduction One of the important duties of a teacher is to observe the student in the classroom, laboratory and
CONSTRUCTION OF AN ACHIEVEMENT TEST Introduction One of the important duties of a teacher is to observe the student in the classroom, laboratory and in other settings. He may also make use of tests in
More informationIntroduction to the Practice of Statistics
Chapter 1: Looking at Data Distributions Introduction to the Practice of Statistics Sixth Edition David S. Moore George P. McCabe Bruce A. Craig Statistics is the science of collecting, organizing and
More informationPhysics 270: Experimental Physics
2017 edition Lab Manual Physics 270 3 Physics 270: Experimental Physics Lecture: Lab: Instructor: Office: Email: Tuesdays, 2 3:50 PM Thursdays, 2 4:50 PM Dr. Uttam Manna 313C Moulton Hall umanna@ilstu.edu
More informationFinancing Education In Minnesota
Financing Education In Minnesota 2016-2017 Created with Tagul.com A Publication of the Minnesota House of Representatives Fiscal Analysis Department August 2016 Financing Education in Minnesota 2016-17
More informationVOL. 3, NO. 5, May 2012 ISSN Journal of Emerging Trends in Computing and Information Sciences CIS Journal. All rights reserved.
Exploratory Study on Factors that Impact / Influence Success and failure of Students in the Foundation Computer Studies Course at the National University of Samoa 1 2 Elisapeta Mauai, Edna Temese 1 Computing
More informationShockwheat. Statistics 1, Activity 1
Statistics 1, Activity 1 Shockwheat Students require real experiences with situations involving data and with situations involving chance. They will best learn about these concepts on an intuitive or informal
More informationStatistical Studies: Analyzing Data III.B Student Activity Sheet 7: Using Technology
Suppose data were collected on 25 bags of Spud Potato Chips. The weight (to the nearest gram) of the chips in each bag is listed below. 25 28 23 26 23 25 25 24 24 27 23 24 28 27 24 26 24 25 27 26 25 26
More informationLEGO MINDSTORMS Education EV3 Coding Activities
LEGO MINDSTORMS Education EV3 Coding Activities s t e e h s k r o W t n e d Stu LEGOeducation.com/MINDSTORMS Contents ACTIVITY 1 Performing a Three Point Turn 3-6 ACTIVITY 2 Written Instructions for a
More informationSeries IV - Financial Management and Marketing Fiscal Year
Series IV - Financial Management and Marketing... 1 4.101 Fiscal Year... 1 4.102 Budget Preparation... 2 4.201 Authorized Signatures... 3 4.2021 Financial Assistance... 4 4.2021-R Financial Assistance
More informationInstructor: Mario D. Garrett, Ph.D. Phone: Office: Hepner Hall (HH) 100
San Diego State University School of Social Work 610 COMPUTER APPLICATIONS FOR SOCIAL WORK PRACTICE Statistical Package for the Social Sciences Office: Hepner Hall (HH) 100 Instructor: Mario D. Garrett,
More informationIndividual Differences & Item Effects: How to test them, & how to test them well
Individual Differences & Item Effects: How to test them, & how to test them well Individual Differences & Item Effects Properties of subjects Cognitive abilities (WM task scores, inhibition) Gender Age
More informationUDW+ Student Data Dictionary Version 1.7 Program Services Office & Decision Support Group
UDW+ Student Data Dictionary Version 1.7 Program Services Office & Decision Support Group 1 Table of Contents Subject Areas... 3 SIS - Term Registration... 5 SIS - Class Enrollment... 12 SIS - Degrees...
More informationMathematics (JUN14MS0401) General Certificate of Education Advanced Level Examination June Unit Statistics TOTAL.
Centre Number Candidate Number For Examiner s Use Surname Other Names Candidate Signature Examiner s Initials Mathematics Unit Statistics 4 Tuesday 24 June 2014 General Certificate of Education Advanced
More informationEECS 571 PRINCIPLES OF REAL-TIME COMPUTING Fall 10. Instructor: Kang G. Shin, 4605 CSE, ;
EECS 571 PRINCIPLES OF REAL-TIME COMPUTING Fall 10 Instructor: Kang G. Shin, 4605 CSE, 763-0391; kgshin@umich.edu Number of credit hours: 4 Class meeting time and room: Regular classes: MW 10:30am noon
More informationINFORMS Transactions on Education
This article was downloaded by: [46.3.195.208] On: 22 November 2017, At: 21:14 Publisher: Institute for Operations Research and the Management Sciences (INFORMS) INFORMS is located in Maryland, USA INFORMS
More informationTHE COLLEGE OF WILLIAM AND MARY IN VIRGINIA INTERCOLLEGIATE ATHLETICS PROGRAMS FOR THE YEAR ENDED JUNE 30, 2005
THE COLLEGE OF WILLIAM AND MARY IN VIRGINIA INTERCOLLEGIATE ATHLETICS PROGRAMS FOR THE YEAR ENDED JUNE 30, 2005 - T A B L E O F C O N T E N T S INDEPENDENT AUDITOR S REPORT ON APPLICATION OF AGREED-UPON
More informationExemplar 6 th Grade Math Unit: Prime Factorization, Greatest Common Factor, and Least Common Multiple
Exemplar 6 th Grade Math Unit: Prime Factorization, Greatest Common Factor, and Least Common Multiple Unit Plan Components Big Goal Standards Big Ideas Unpacked Standards Scaffolded Learning Resources
More informationMathematics subject curriculum
Mathematics subject curriculum Dette er ei omsetjing av den fastsette læreplanteksten. Læreplanen er fastsett på Nynorsk Established as a Regulation by the Ministry of Education and Research on 24 June
More informationSMALL GROUPS AND WORK STATIONS By Debbie Hunsaker 1
SMALL GROUPS AND WORK STATIONS By Debbie Hunsaker 1 NOTES: 2 Step 1: Environment First: Inventory your space Why: You and your students will be much more successful during small group instruction if you
More informationCollege Pricing. Ben Johnson. April 30, Abstract. Colleges in the United States price discriminate based on student characteristics
College Pricing Ben Johnson April 30, 2012 Abstract Colleges in the United States price discriminate based on student characteristics such as ability and income. This paper develops a model of college
More informationChapters 1-5 Cumulative Assessment AP Statistics November 2008 Gillespie, Block 4
Chapters 1-5 Cumulative Assessment AP Statistics Name: November 2008 Gillespie, Block 4 Part I: Multiple Choice This portion of the test will determine 60% of your overall test grade. Each question is
More informationSeminar - Organic Computing
Seminar - Organic Computing Self-Organisation of OC-Systems Markus Franke 25.01.2006 Typeset by FoilTEX Timetable 1. Overview 2. Characteristics of SO-Systems 3. Concern with Nature 4. Design-Concepts
More informationGenerating Test Cases From Use Cases
1 of 13 1/10/2007 10:41 AM Generating Test Cases From Use Cases by Jim Heumann Requirements Management Evangelist Rational Software pdf (155 K) In many organizations, software testing accounts for 30 to
More informationOCR LEVEL 3 CAMBRIDGE TECHNICAL
Cambridge TECHNICALS OCR LEVEL 3 CAMBRIDGE TECHNICAL CERTIFICATE/DIPLOMA IN IT SYSTEMS ANALYSIS K/505/5481 LEVEL 3 UNIT 34 GUIDED LEARNING HOURS: 60 UNIT CREDIT VALUE: 10 SYSTEMS ANALYSIS K/505/5481 LEVEL
More informationNew Features & Functionality in Q Release Version 3.2 June 2016
in Q Release Version 3.2 June 2016 Contents New Features & Functionality 3 Multiple Applications 3 Class, Student and Staff Banner Applications 3 Attendance 4 Class Attendance 4 Mass Attendance 4 Truancy
More informationREADY TO WORK PROGRAM INSTRUCTOR GUIDE PART I
READY TO WORK PROGRAM INSTRUCTOR GUIDE PART I LESSON TITLE: Problem Solving Tools Method: Informal Lecture, Guided Discussion EDUCATIONAL OBJECTIVE: Comprehend the many different uses of quality/problem
More informationAUTOMATED TROUBLESHOOTING OF MOBILE NETWORKS USING BAYESIAN NETWORKS
AUTOMATED TROUBLESHOOTING OF MOBILE NETWORKS USING BAYESIAN NETWORKS R.Barco 1, R.Guerrero 2, G.Hylander 2, L.Nielsen 3, M.Partanen 2, S.Patel 4 1 Dpt. Ingeniería de Comunicaciones. Universidad de Málaga.
More informationGuidelines for Project I Delivery and Assessment Department of Industrial and Mechanical Engineering Lebanese American University
Guidelines for Project I Delivery and Assessment Department of Industrial and Mechanical Engineering Lebanese American University Approved: July 6, 2009 Amended: July 28, 2009 Amended: October 30, 2009
More informationLecture 15: Test Procedure in Engineering Design
MECH 350 Engineering Design I University of Victoria Dept. of Mechanical Engineering Lecture 15: Test Procedure in Engineering Design 1 Outline: INTRO TO TESTING DESIGN OF EXPERIMENTS DOCUMENTING TESTS
More informationUtilizing Soft System Methodology to Increase Productivity of Shell Fabrication Sushant Sudheer Takekar 1 Dr. D.N. Raut 2
IJSRD - International Journal for Scientific Research & Development Vol. 2, Issue 04, 2014 ISSN (online): 2321-0613 Utilizing Soft System Methodology to Increase Productivity of Shell Fabrication Sushant
More informationSchool Size and the Quality of Teaching and Learning
School Size and the Quality of Teaching and Learning An Analysis of Relationships between School Size and Assessments of Factors Related to the Quality of Teaching and Learning in Primary Schools Undertaken
More informationMeasures of the Location of the Data
OpenStax-CNX module m46930 1 Measures of the Location of the Data OpenStax College This work is produced by OpenStax-CNX and licensed under the Creative Commons Attribution License 3.0 The common measures
More informationCollege Pricing and Income Inequality
College Pricing and Income Inequality Zhifeng Cai U of Minnesota, Rutgers University, and FRB Minneapolis Jonathan Heathcote FRB Minneapolis NBER Income Distribution, July 20, 2017 The views expressed
More informationlearning collegiate assessment]
[ collegiate learning assessment] INSTITUTIONAL REPORT 2005 2006 Kalamazoo College council for aid to education 215 lexington avenue floor 21 new york new york 10016-6023 p 212.217.0700 f 212.661.9766
More informationBroward County Public Schools G rade 6 FSA Warm-Ups
Day 1 1. A florist has 40 tulips, 32 roses, 60 daises, and 50 petunias. Draw a line from each comparison to match it to the correct ratio. A. tulips to roses B. daises to petunias C. roses to tulips D.
More informationResearch Design & Analysis Made Easy! Brainstorming Worksheet
Brainstorming Worksheet 1) Choose a Topic a) What are you passionate about? b) What are your library s strengths? c) What are your library s weaknesses? d) What is a hot topic in the field right now that
More informationTotalLMS. Getting Started with SumTotal: Learner Mode
TotalLMS Getting Started with SumTotal: Learner Mode Contents Learner Mode... 1 TotalLMS... 1 Introduction... 3 Objectives of this Guide... 3 TotalLMS Overview... 3 Logging on to SumTotal... 3 Exploring
More informationDEPARTMENT OF FINANCE AND ECONOMICS
Department of Finance and Economics 1 DEPARTMENT OF FINANCE AND ECONOMICS McCoy Hall Room 504 T: 512.245.2547 F: 512.245.3089 www.fin-eco.mccoy.txstate.edu (http://www.fin-eco.mccoy.txstate.edu) The mission
More informationIntroduction on Lean, six sigma and Lean game. Remco Paulussen, Statistics Netherlands Anne S. Trolie, Statistics Norway
Introduction on Lean, six sigma and Lean game Remco Paulussen, Statistics Netherlands Anne S. Trolie, Statistics Norway 1 Lean is. a philosophy a method a set of tools Waste reduction User value Create
More informationLearning Microsoft Office Excel
A Correlation and Narrative Brief of Learning Microsoft Office Excel 2010 2012 To the Tennessee for Tennessee for TEXTBOOK NARRATIVE FOR THE STATE OF TENNESEE Student Edition with CD-ROM (ISBN: 9780135112106)
More informationACTL5103 Stochastic Modelling For Actuaries. Course Outline Semester 2, 2014
UNSW Australia Business School School of Risk and Actuarial Studies ACTL5103 Stochastic Modelling For Actuaries Course Outline Semester 2, 2014 Part A: Course-Specific Information Please consult Part B
More informationNew Program Process, Guidelines and Template
New Program Process, Guidelines and Template This document outlines the process and guidelines for the Florida Tech academic units to introduce new programs (options, minors, degree, for-credit certificate
More informationCENTRAL MAINE COMMUNITY COLLEGE Introduction to Computer Applications BCA ; FALL 2011
CENTRAL MAINE COMMUNITY COLLEGE Introduction to Computer Applications BCA 120-03; FALL 2011 Instructor: Mrs. Linda Cameron Cell Phone: 207-446-5232 E-Mail: LCAMERON@CMCC.EDU Course Description This is
More informationHow to set up gradebook categories in Moodle 2.
How to set up gradebook categories in Moodle 2. It is possible to set up the gradebook to show divisions in time such as semesters and quarters by using categories. For example, Semester 1 = main category
More informationBMBF Project ROBUKOM: Robust Communication Networks
BMBF Project ROBUKOM: Robust Communication Networks Arie M.C.A. Koster Christoph Helmberg Andreas Bley Martin Grötschel Thomas Bauschert supported by BMBF grant 03MS616A: ROBUKOM Robust Communication Networks,
More informationInstitutionen för datavetenskap. Hardware test equipment utilization measurement
Institutionen för datavetenskap Department of Computer and Information Science Final thesis Hardware test equipment utilization measurement by Denis Golubovic, Niklas Nieminen LIU-IDA/LITH-EX-A 15/030
More informationProbability estimates in a scenario tree
101 Chapter 11 Probability estimates in a scenario tree An expert is a person who has made all the mistakes that can be made in a very narrow field. Niels Bohr (1885 1962) Scenario trees require many numbers.
More informationDocument number: 2013/ Programs Committee 6/2014 (July) Agenda Item 42.0 Bachelor of Engineering with Honours in Software Engineering
Document number: 2013/0006139 Programs Committee 6/2014 (July) Agenda Item 42.0 Bachelor of Engineering with Honours in Software Engineering Program Learning Outcomes Threshold Learning Outcomes for Engineering
More informationAPPENDIX A: Process Sigma Table (I)
APPENDIX A: Process Sigma Table (I) 305 APPENDIX A: Process Sigma Table (II) 306 APPENDIX B: Kinds of variables This summary could be useful for the correct selection of indicators during the implementation
More informationReinforcement Learning by Comparing Immediate Reward
Reinforcement Learning by Comparing Immediate Reward Punit Pandey DeepshikhaPandey Dr. Shishir Kumar Abstract This paper introduces an approach to Reinforcement Learning Algorithm by comparing their immediate
More informationRover Races Grades: 3-5 Prep Time: ~45 Minutes Lesson Time: ~105 minutes
Rover Races Grades: 3-5 Prep Time: ~45 Minutes Lesson Time: ~105 minutes WHAT STUDENTS DO: Establishing Communication Procedures Following Curiosity on Mars often means roving to places with interesting
More informationAP Statistics Summer Assignment 17-18
AP Statistics Summer Assignment 17-18 Welcome to AP Statistics. This course will be unlike any other math class you have ever taken before! Before taking this course you will need to be competent in basic
More informationMathematics process categories
Mathematics process categories All of the UK curricula define multiple categories of mathematical proficiency that require students to be able to use and apply mathematics, beyond simple recall of facts
More informationAn Estimating Method for IT Project Expected Duration Oriented to GERT
An Estimating Method for IT Project Expected Duration Oriented to GERT Li Yu and Meiyun Zuo School of Information, Renmin University of China, Beijing 100872, P.R. China buaayuli@mc.e(iuxn zuomeiyun@263.nct
More informationILLINOIS DISTRICT REPORT CARD
-6-525-2- HAZEL CREST SD 52-5 HAZEL CREST SD 52-5 HAZEL CREST, ILLINOIS and federal laws require public school districts to release report cards to the public each year. 2 7 ILLINOIS DISTRICT REPORT CARD
More information36TITE 140. Course Description:
36TITE 140 36TSpreadsheet Software Course Description: 11TCovers use of spreadsheet software to create spreadsheets with formatted cells and cell ranges, control pages, multiple sheets, charts and macros.
More informationA Pipelined Approach for Iterative Software Process Model
A Pipelined Approach for Iterative Software Process Model Ms.Prasanthi E R, Ms.Aparna Rathi, Ms.Vardhani J P, Mr.Vivek Krishna Electronics and Radar Development Establishment C V Raman Nagar, Bangalore-560093,
More informationILLINOIS DISTRICT REPORT CARD
-6-525-2- Hazel Crest SD 52-5 Hazel Crest SD 52-5 Hazel Crest, ILLINOIS 2 8 ILLINOIS DISTRICT REPORT CARD and federal laws require public school districts to release report cards to the public each year.
More informationScienceDirect. Noorminshah A Iahad a *, Marva Mirabolghasemi a, Noorfa Haszlinna Mustaffa a, Muhammad Shafie Abd. Latif a, Yahya Buntat b
Available online at www.sciencedirect.com ScienceDirect Procedia - Social and Behavioral Scien ce s 93 ( 2013 ) 2200 2204 3rd World Conference on Learning, Teaching and Educational Leadership WCLTA 2012
More informationRadius STEM Readiness TM
Curriculum Guide Radius STEM Readiness TM While today s teens are surrounded by technology, we face a stark and imminent shortage of graduates pursuing careers in Science, Technology, Engineering, and
More information